Day 205 – Drywall Next!

Now that the stone work has completed outside and in, and beautifully I might add, the quicker bulk work can commence. Insulation has zipped along and is now mostly complete with only a few hours of touch-up to do. Following this is the task of carefully applying a 6mil poly vapour barrier on all walls. The vapour barrier keeps water vapour and dust from passing back and forth between the outside, the inside of the wall and the interior air volume of the home. In order for this to work, the poly has to be applied carefully to avoid tears and gaps – taping all seams.

Following this, the drywall is scheduled to commence next week and will require approximately a months work before we can get to the next big ticket items; radiant floor and poured concrete with topping. Info to come.